The installed generating capacity of the North Board's system , which was 243 MW in 1948 , had grown to 1,062 MW in 1961. 83 per cent . of this is in 44 hydro stations ( of which 42 were commissioned during the period ) ; two thermal ...
The installed generating capacity of the North Board's system , which was 243 MW in 1948 , had grown to 1,062 MW in 1961. 83 per cent . of this is in 44 hydro stations ( of which 42 were commissioned during the period ) ; two thermal ...
Seite 75
Generating Plant Capacity 139. The generating plant output capacity in Scotland at the end of 1961 totalled 2,858 MW . Additional plant with an output capacity of 2,672 MW has been authorised which , when account is taken of the 249 MW ...
Generating Plant Capacity 139. The generating plant output capacity in Scotland at the end of 1961 totalled 2,858 MW . Additional plant with an output capacity of 2,672 MW has been authorised which , when account is taken of the 249 MW ...
Seite 76
Figure 18 shows that , according to present estimates , in order to meet the need in 1975 , further generating plant with an output capacity of about 3,000 MW will have to be authorised , and that by 1980 a still further 2,000 MW of ...
Figure 18 shows that , according to present estimates , in order to meet the need in 1975 , further generating plant with an output capacity of about 3,000 MW will have to be authorised , and that by 1980 a still further 2,000 MW of ...
Was andere dazu sagen - Rezension schreiben
Es wurden keine Rezensionen gefunden.
Inhalt
Annual Report and Accounts including the Report of the Electricity | i |
CONSTITUTION OF THE BOARD AND ADVISORY COMMITTEES | 4 |
TRANSMISSION | 9 |
55 weitere Abschnitte werden nicht angezeigt.
Andere Ausgaben - Alle anzeigen
Häufige Begriffe und Wortgruppen
accidents addition amount annual APPENDIX assistance Association Authority average Board boats brigades building capacity capital carried catch caused cent changes charges close coast Committee compared completed connection considerable construction consumers continued cost Council course December demand distribution District drift-net effect electricity engineering estimated examination experiments explosion Factories Fatal figures fire fishery fishing further given grounds heading hydro important improvement increase industry installation interest kilowatts landings lead less limited load March methods million nets North obtained Officer operation particular period persons plant ports possible present production received recorded Regulations Report Research river safety salmon schemes Scotland Scottish season showed South stations stocks supply TABLE taken thermal Total unit vessels