Seite 4
... install ( as part of the 1967 Programme ) a further 720 MW of gas turbine plant , the greater part of which is ... installed in the single year 1968 , but it is proposed to install more than half the extra plant in 1968 ( detailed ...
... install ( as part of the 1967 Programme ) a further 720 MW of gas turbine plant , the greater part of which is ... installed in the single year 1968 , but it is proposed to install more than half the extra plant in 1968 ( detailed ...
Seite 10
... installed capacity of 34,211 MW . Their maximum output capacity , 31,687 MW , was 9.4 per cent . more than the total in March 1962. Technical details of generators and boilers in each station are given in Appendix 1 , which also ...
... installed capacity of 34,211 MW . Their maximum output capacity , 31,687 MW , was 9.4 per cent . more than the total in March 1962. Technical details of generators and boilers in each station are given in Appendix 1 , which also ...
Seite 32
... Installed generating capacity Maximum output capacity MW MW s.o. New plant brought into commission +2,950.5 +2,689 Plant recommissioned + 5 + 5 Revised rating of existing plant ( see paragraph 67 ) + 55 + 62 2 Plant shut down ( see ...
... Installed generating capacity Maximum output capacity MW MW s.o. New plant brought into commission +2,950.5 +2,689 Plant recommissioned + 5 + 5 Revised rating of existing plant ( see paragraph 67 ) + 55 + 62 2 Plant shut down ( see ...
Inhalt
INTRODUCTION | 9 |
Road Safety for School Children | 36 |
FURTHER EDUCATION | 51 |
34 weitere Abschnitte werden nicht angezeigt.
Andere Ausgaben - Alle anzeigen
Häufige Begriffe und Wortgruppen
31 March Appendix appointed approved Area Boards arrangements average awarded Bradwell British Electricity Authority cables capital cent Central Electricity central institutions certificated teachers charges coal colleges of education Committee consumers continued courses East Midlands Education Authorities Education in Scotland Education Scotland Electricity Board Electricity Council Electricity Generating Board electricity supply engineering expenditure functions further education further education centres gas turbine governing bodies Hinkley Point increase industry installed interest kilowatt-hours supplied kilowatts load main transmission maximum demand ment Midlands million kWh Minister National North Western number of kilowatt-hours operation organisation overhead lines paragraph period plant primary professional programme pupils qualifications reactor recommend Region Regulations Report scheme Scotland Scottish Council Scottish Education Department secondary schools Secretary South staff steam substations Table Teaching Council teaching profession Thames Division thermal Total Training of Teachers voltage Wylfa