This chapter describes the Board's operational plant and equipment at the end of
March 1963. Power Stations 31. The Generating Board owned 236 power
stations in England and Wales at the end of March 1963, with a total installed
capacity ...
This chapter describes the Board's operational plant and equipment at the end of
March 1963. Power Stations 31. The Generating Board owned 236 power
stations in England and Wales at the end of March 1963, with a total installed
capacity ...
Seite 155
Appendix 3 Number and size of power stations Total installed capacity of power
Installed capacity at Number of power stations stations in group individual
stations at 31 March 1963 March March March - MW 1924–5 1939–40 1953
1962 1963 ...
Appendix 3 Number and size of power stations Total installed capacity of power
Installed capacity at Number of power stations stations in group individual
stations at 31 March 1963 March March March - MW 1924–5 1939–40 1953
1962 1963 ...
Seite 118
THE ELECTRICITY COUNCIL AND THE ELECTRICITY BOARDS IN ENGLAND
AND WALES Consolidated Statement of Accounts for the Year ended 31st March
, 1963 Investments of the Electricity Council (Notes on Accounts: Paragraph 19) l
...
THE ELECTRICITY COUNCIL AND THE ELECTRICITY BOARDS IN ENGLAND
AND WALES Consolidated Statement of Accounts for the Year ended 31st March
, 1963 Investments of the Electricity Council (Notes on Accounts: Paragraph 19) l
...
Was andere dazu sagen - Rezension schreiben
Es wurden keine Rezensionen gefunden.
Andere Ausgaben - Alle anzeigen
Häufige Begriffe und Wortgruppen
addition amount appointed approved Area Area Boards arrangements Association average awarded Board bodies capacity capital cent Central centres Certificate changes charges classes coal colleges colleges of education Committee completed consider consideration construction consumers continued cost Council courses demand Department detailed Education Authorities effect Electricity engineering established estimated existing expenditure experience financing fuel functions further given governing grants higher increase industry installed institutions interest lines load March matters maximum million North nuclear officers operation organisation paragraph period planned plant power stations practice present primary profession professional programme pupils qualifications received recommend Region Regulations relation Report representatives scheme schools Scotland Scottish secondary Secretary South staff standards steam supply Table teachers teaching technical transmission Type units universities