... Claims 66. When a variation of either type is made in a contract , the engineer of the Employing Authority must provide the contractor with a written or verbal variation order , defining the alterations desired in the works1 . The ...
... Claims 66. When a variation of either type is made in a contract , the engineer of the Employing Authority must provide the contractor with a written or verbal variation order , defining the alterations desired in the works1 . The ...
Seite xxviii
... claims ( Q. 405 , 408 , 667 ) , resulting in extra work for both contractors in mounting the claim and for ... claims , but asserted that highway authorities were more frequently slow in settling them ( Q. 1237-40 ) . The ...
... claims ( Q. 405 , 408 , 667 ) , resulting in extra work for both contractors in mounting the claim and for ... claims , but asserted that highway authorities were more frequently slow in settling them ( Q. 1237-40 ) . The ...
Seite 109
... claims from contractors , is it true that the settlement of some of the main sums in the contract is delayed until the conse- quential claims have been settled ? - No , Sir , not as a rule . We usually pay up to a certain point . 402 ...
... claims from contractors , is it true that the settlement of some of the main sums in the contract is delayed until the conse- quential claims have been settled ? - No , Sir , not as a rule . We usually pay up to a certain point . 402 ...
Inhalt
39665 | 1 |
APPENDICES | 32 |
COUNTY COUNCILS ASSOCIATION | 54 |
9 weitere Abschnitte werden nicht angezeigt.
Andere Ausgaben - Alle anzeigen
Häufige Begriffe und Wortgruppen
13 February A. C. NEWMAN administrative allocation amount approval arbitration Area Finance Officers Association Banwell bridge cent Chairman Civil Engineers claims classified roads Clyde Tunnel Committee construction consultation Continued contract contractor conurbation cost county boroughs county surveyors deal delay Divisional Road Engineer estimated evidence expenditure figures Frank Markham Glasgow Government gramme Harold Davies highway authorities improvement schemes increase J. N. WOOD Kinlochmoidart large burghs London County Council maintenance and minor major Marchant ment metropolitan boroughs Minister Ministry of Housing Ministry of Transport Ministry's minor improvements motorways Norman Pannell organisation paragraph particular payment present priorities proposals question R. N. HEATON redevelopment Report responsibility road improvements road schemes Scotland Scottish Home Department Sir Gerald staff standards statutory Sub-Committee suggest tender thing tion town Treasury trunk roads urban variations War Office WARDLEY Whitefoord Woof