Parliamentary Papers, Band 16 |
Im Buch
Ergebnisse 1-3 von 74
Seite 27
Market APPENDIX IV- ( continued ) Work Involved and Purpose The replacement of two 10 MVA 22/11 kV transformers by two 20 MVA 33/11 kV units supplied by 33 kV connections from Stanmore Grid Substation to restore firm capacity .
Market APPENDIX IV- ( continued ) Work Involved and Purpose The replacement of two 10 MVA 22/11 kV transformers by two 20 MVA 33/11 kV units supplied by 33 kV connections from Stanmore Grid Substation to restore firm capacity .
Seite 2
The three largest of these , each having four transformers each with a capacity of 15,000 kVA 33/11 kV , were at Churchfields Road , Beckenham , Ley Street , Ilford and Trinity Crescent , Tooting . 13. Transforming capacity was ...
The three largest of these , each having four transformers each with a capacity of 15,000 kVA 33/11 kV , were at Churchfields Road , Beckenham , Ley Street , Ilford and Trinity Crescent , Tooting . 13. Transforming capacity was ...
Seite 26
APPENDIX II — continued SECONDARY POINTS OF SUPPLY FROM POWER STATIONS BELONGING TO THE CENTRAL ELECTRICITY GENERATING BOARD BUT CONNECTED TO THE BOARD'S NETWORK ONLY Power Station Installed capacity of generators Voltage of supply .
APPENDIX II — continued SECONDARY POINTS OF SUPPLY FROM POWER STATIONS BELONGING TO THE CENTRAL ELECTRICITY GENERATING BOARD BUT CONNECTED TO THE BOARD'S NETWORK ONLY Power Station Installed capacity of generators Voltage of supply .
Was andere dazu sagen - Rezension schreiben
Es wurden keine Rezensionen gefunden.
Inhalt
ACCOUNTS | 26 |
CONTENTS | 53 |
New Maximum Demand Tariff for 196364 | 8 |
98 weitere Abschnitte werden nicht angezeigt.
Andere Ausgaben - Alle anzeigen
Häufige Begriffe und Wortgruppen
Account additional Alderman amount annual APPENDIX appointed Area assets Authorities average Balance bulk supply capacity capital carried cent Central Chairman charges Committee completed connected Consultative Council consumers continued Contracting contributions cost Councillor courses Depreciation Deputy Chairman distribution District domestic Eastern Electricity ELECTRICITY BOARD Electricity Council employees ended 31st March engineering estimated existing expenditure expenses Farm financing fixed further given heating House improve Income increase industrial installation interest January less lighting load Local London Manager maximum demand meet meter miles million Minister months North NOTES off-peak Officers operation period points Power premises proposals purchase reading received record reduced reinforcement Report Reserve respect Revenue Account Road rural Salaries scheme shown South staff Statement Station Street substation Superannuation supply taken Tariff transferred transformer unit sold voltage volts Wales West